Project Timeline

Project Timeline

Warperup Creek is under early active development. Vestas is consulting with local community members and stakeholders about the project. The feedback received, in conjunction with the results of environmental assessments, will inform the project design.

2022-2024

Site Identification

2022-2024

2022

Wind assessment begins

2022

2023

Community consultation begins

2023

2025

Environmental Studies Begin

2025

2026

Environmental Protection Authority (EPA) Referral

2026

2027

Environment Protection and Biodiversity Conservation (EPBC) Act referral

2027

2027

Environmental Review Document (ERD) goes on public display

2027

2028

 Permitting completion

2028

2029

Grid connection

2029

2030

 Begin construction

2030